top of page

CONTRACT LAW May (2026) CONTRACT LAW UPDATES AND JUDGMENTS

  • 2 days ago
  • 1 min read

The Court observed that under the contractual clause, the contractor was required to notify the Engineer-in-Charge within 30 days of imposition of any additional tax or levy, along with supporting details. It held that the award of simple interest at the rate of 9% by the arbitrator did not warrant interference within the limited scope of Section 34 of the Arbitration and Conciliation Act, 1996, as it was neither excessive nor unreasonable.




Comments


SUBSCRIBE TO OUR NEWSLETTER

Get updates on the latest publications, judgements, policy updates, webinars, reports and much more.

Thank you for subscribing!

bottom of page